So, our basement and garage concrete slabs were poured on Wednesday. Of course, my camera had a dead battery. Thursday our framing was started. On Friday afternoon the first floor was there!!!
Our project manager sent his weekly email and said that the framing should be done early/mid year and then the HVAC, plumber, and electrician will all come and do their thing by the end of next week. Our pre-drywall meeting will be in about 1.5 weeks! How exciting is that?!?!
The first steps of framing (July 22, 2010)
The first floor! July 23, 2010